Funding Wildlife Ponds and Wetlands in Devon: What to Have Ready
For a charity or council planning a wildlife pond or wetland in Devon, the first funding question is whether the site and the proposed work qualify. Check that before spending money on surveys or designs. The Veolia Environmental Trust’s Habitat and Biodiversity Grant is one route for projects that are already far enough along to deliver physical habitat improvements.
Current round: opens 26 November 2026 and closes at noon on 7 January 2027. The scheduled decision date is 2 March 2027. The usual grant request is £10,000–£75,000. Read the Habitat and Biodiversity Grant criteria and check the latest round dates before applying.
Which pond and wetland projects could fit?
A seasonal scrape in the right place can add shallow-water habitat. An existing pond may be better restored than replaced, for example by selectively removing accumulated silt and recovering shallow margins while keeping the established habitat around it. Native marginal planting can form part of either project. Start with what already lives on the site and how water moves through it, rather than assuming the work needs a new pond.

What to have ready before applying
- An eligible applicant and site. The scheme is for eligible not-for-profit organisations, local authorities and Environmental Bodies. The work must be on one site within 10 miles of an eligible landfill in England. Use Veolia’s eligibility checker rather than assuming a Devon postcode qualifies.
- Land rights and permissions. Check who owns the land and get the relevant approvals before applying. If you lease the land, Veolia normally requires at least seven years left on the lease. Its criteria also set out a route for certain partnerships on council-owned land.
- A design that can be priced. Put the work on a plan and show the existing features to retain. Set out how the pond or wetland will fill and drain, how machinery will reach it, where excavated soil will go and who will look after it. Allow separately for feasibility, surveys and design rather than relying on the grant to pay for them.
- The separate third-party contribution. Veolia asks for evidence that this is secured when you apply. It is 10% of the grant amount, paid to the landfill operator before the grant is released. For a £30,000 grant, that’s a separate £3,000 payment. See Veolia’s third-party contribution guidance.
Get a price without appointing a contractor
You can start a tender before applying, but don’t appoint a contractor at that stage. Veolia checks for competitive quotes after a conditional award and requires at least three for each contracted element. Don’t start work until it gives formal consent. Give everyone the same quantities, access arrangements, spoil handling and finishing requirements so you can compare prices on the same basis. Read Veolia’s application and award process.
Need a contractor’s price for pond or wetland works?
SAS Aquatics is a pond and wetland contractor working with land managers and conservation teams. We can review an outline scope for practical delivery, price agreed earthworks, pond restoration or planting, and tender against an existing specification. The eligible organisation remains the applicant and runs its own procurement.
If you have a Devon site in mind, send us the location, a plan or photographs, what you want to achieve and your deadline. If you already have drawings or a specification, include those so we can see exactly what needs pricing.
Funding information checked 24 November 2026. Confirm current criteria and dates directly with the Trust.